on 02-27-2019 2:20 AM
Today we are using BW/4hana but is not the newest Support package , I have seen in some blogs regarding the BW4hana admin cockpit , the question is if we do the upgrade of SP we are going to lose the access to SAPGUI RSPC to create and execute the Pchains? or not only we will have one more option to monitor and create the Pchians ...
Hi,
GUI maintenance of process chains will be still available if you upgrade to 1.0 SP8. You can use both cockpit and GUI.
BW4/HANA 2.0 offers process chain integration in Eclipse. It's released yesterday, I didn't check yet but it will probably remove GUI option.
Regards,
Erdem