Hi Guys,

One of my client is manufacturing of Electronic product (MTO scenario with Product Cost by Sales Order), they want to use the project system to keep track of product manufacturing ( complete PP should be track in PS system).

i did the following

1. Sales Order Created,

2. Automatically WBS element will be created,

3. PP is integrated with PS

My question is that when I run MRP, the system will create PR and Planned order as per the Sales order Qty or not or else it will look for Demand from the PS system for creating PR and Planned order.

How the system will work,I totally confused, kindly clarify

I can create PS as statistical order if require, i think this scenario, PS and PP is statistical only, because Sales Order is my CO object and am doing costing at Sales Order level.

Kindly clear my doubts and give me idea how the system will work.

Thanks in advance.

Regards

Elangovan