Skip to Content
avatar image
Former Member

CJ40 Detailed Planning options not active

Hi Experts

I wish to do Detailed Cost Planning for my WBS elements, but when I go to transaction CJ40 >> Extras >> Detailed Planning, the options are grayed out (inactive). So I am not able to do detailed Planning through CJ40.

Can sombody have an idea how it can be rectified.

Thanks

JOHRI

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Aug 19, 2010 at 07:09 AM

    I think you are trying to access detailed planning from CJ40 in overall value screen. Detailed planning is available for fiscal year wise. Change the period from overall to any current or any fiscal year and now check again, detailed planning will be active now

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 19, 2010 at 07:07 AM

    Check your planning profile - OPSB have you maintained relevant CE group /Costing Variant etc ?

    With Regards

    Nitin P.

    Add comment
    10|10000 characters needed characters exceeded