Project Cost Plan 2 in CN41N

Hi,

In CN41N there is column "Proj. Cost Plan 2".

Presssing Help on it is showing " Project cost plan (version 2)

Project cost plan: comparative version".

I am unable to understand from where this cost is coming. Kindly Help.

Thanks,

Harsh.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 18, 2010 at 10:08 AM

    Hi Harsh,

    Check if costs have been planned in some other version other than 0.

    Regards,

    Gokul

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 18, 2010 at 10:08 AM

    If you have planned costs for version 1 other than version 0, you will seee the planned cost of version 1 in that column.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 18, 2010 at 11:36 AM

    Project COst Plan Column; Value comes from CO version '0'.

    Project COst Plan 2 Column; Value comes from CO version '1'.