I get a problem, one of the existing projects has been marked "TECO" , but this opeartion was not done by our project manager.

so could someone can teach me how to check the modification history.

thanks in advance

Meng HM

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Aug 18, 2010 at 05:46 AM

    I request you to search in forum before you post. This question is posted by many and replied with solutions.

    With Regards

    Nitin P.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 18, 2010 at 05:50 AM

    Hi,

    In transaction CJ02, choose the WBS element click on "i" button at the bottom of the screen, choose from the menu options

    Extras --> Change Documents --> All.

    Praveen

    Add comment
    10|10000 characters needed characters exceeded

    • Meng, what praveen has suggested will not work in each and every case...there are some prerequisites for that. Follow what Nitin has suggested, search the forum, you will know the prerequisite also, that is the best solution.