Capturing Plant & machinery Cost while planning

Please advice, how to capture plant and machinery cost while planning in PS on activity basis.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Aug 17, 2010 at 05:29 AM

    Talk to your FICO consultant, they may help you on this.

    Add comment
    10|10000 characters needed characters exceeded

    • Networks can allow you to plan costs via objects called Network activities. Material components can be assigned to a network activity in CJ20N. Each activity can have a list of Material components. All these costs for the materials are shown as Planned costs in plan Version 0.

  • avatar image
    Former Member
    Aug 17, 2010 at 06:36 AM

    You can define your plant-machinery as 'work center' which is helping you manufacture the goods required in the project, you should use thse plant-machinery as a work center. You can define the operating rate for this plant-machinery. when you are suing this plant-machinery as work cneter in network activity, the planned costs will be calculated. Also when you post the activity confirmation, actual costs will be posted on network activity.

    For detailed configuration take help of CO consultant on setting this up.

    Regards,

    Mahendra Dighe

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 17, 2010 at 06:51 AM

    Hi,

    The most simple and standard way has been explained by Mahendra. You can follow that to achieve your objective. Else you can go through SAP Help to know more about using PRT's in the project.

    Regards,

    Gokul