How can we assign a production order to the network or vice versa.
I know the WBS can be assigned to production order through assignment tab in production order.
Thanks,
Santhosh
Hi,
When you create Planned Order, There in the assignment tab, select the "Assignment Category" as 'N' and then you will be able to assign Planned Order to Network. After that Convert it to PO as normal.
Regards,
Harsh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your response
however while creating the planned order iam encountering the below message
"Account assignment category N invalid"
Message no. 61143
suggest me which planned order profile to be used while creating planned order with transaction MD11
Please also explain me where to assign the network in production order
Thanks,
Santhosh
Edited by: SANTHOSHCH on Aug 14, 2010 8:56 AM