Assignment of production order to network

Former Member
0 Kudos

Hi,

How can we assign a production order to the network or vice versa.

I know the WBS can be assigned to production order through assignment tab in production order.

Thanks,

Santhosh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

When you create Planned Order, There in the assignment tab, select the "Assignment Category" as 'N' and then you will be able to assign Planned Order to Network. After that Convert it to PO as normal.

Regards,

Harsh.

Former Member
0 Kudos

Thanks for your response

however while creating the planned order iam encountering the below message

"Account assignment category N invalid"

Message no. 61143

suggest me which planned order profile to be used while creating planned order with transaction MD11

Please also explain me where to assign the network in production order

Thanks,

Santhosh

Edited by: SANTHOSHCH on Aug 14, 2010 8:56 AM

Former Member
0 Kudos

Hi,

Some settings in OPPQ might be required. Do a search on internet, you will find many discussions on this.

Regards,

Harsh.

Former Member
0 Kudos

Try with Account assignment category as "Q".

I hope this suffices the requirement.

Please let me know if it doesn't work.

Best Regards,

Krishna Singh