on 02-24-2019 2:34 PM
Hi
I have configured new costing type to update Profit Center valuation view, configured new Costing variant and run CK11n, its picking activity cost perfectly, the issue is (material quantity is showing but material cost is not calculating)
Following message :
Message no.CK361
Diagonosis: The cost estimate contains an item with Material Component, which although having no errors was costed with a value of zero.
Procedure: Check the item with number 00007 in the itemization of the assembly concerned.
Thanks