Hi Friends,
We are having requirement of assigning 20000 materials to single Inspection Plan ( since same characteristics need to be checked for each material). I have initially made Inspection plan with out assigning any material, now to the group already created i want to assign 20000 materials (using T code QP02).
My problem is assigning of these 20 k materials to a single group. Manually at a time only 14 materials cab be assigned, tried to make LSMW but the process is very slow as you need to do page down many times (20000/ 14).
Can anybody suggest the faster way of assigning these materials?
Thanks and Regards,
Shekhar