How to restrict quantity like cost

Cane we restrict on quantity, as we do the cost with budget functionality. If yes, pl. explain how to do.

Zinni

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 16, 2010 at 03:27 AM

    I agree with Nitin, SAP doesn't have the functionality to manage the project cost based on quantity (not value)

    AFAIK, there's no ERP system that has this functionality (unless it's customized), CMIIW

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 13, 2010 at 06:49 AM

    Request you to clarify in details, as it is not clear.

    With Regards

    Nitin P.

    Add comment
    10|10000 characters needed characters exceeded

    • According to me what is speical need based on quantity cost control. If you wanted to control via Quantiity than you can create PO for only required quantity and if you not sure of requried quantitiy than make annual of period contract use it for your requirement.

      I think budget control based on quantity is not there.

      With Regards

      Nitin P.