Hi Team,

We have created a process chain for consolidation function as required by client, but we want the process chain to check the preceding task status and only on successfully completion it should proceed to next task. Is there a standard program or function module which does this, please update.

Also we would like to pass dynamic permanent parameter values for the variants of task.

Thanks in advance.

Kind Regards

Sridhar

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Sridhar,

Your ID represets a company and its not fare use company name as ID.

It would be better if you can use your personal IDs instead of comany name.

Thanks

Kamal

former_member209721
Active Contributor
0 Kudos

Sorry, which functions exactly do you execute via a process chain ?

0 Kudos

Hi Collet,

We have created a process chain as below:

Period Initialization - Data Collection -LDS - Calculation of RE - Validation of RFD - Interunit Elimination -COI.

I have created the Separate variants for each of the above functions with program UCBATCH01.and the process chain is working fine.

But we want the process chain to check the task status before it proceed to next task execution and stop if any error occurs in the task. Also we want the dynamic selection of parameters from Permanent Parameters of Consolidation Monitor.

Kind Regards

sridhar

former_member209721
Active Contributor
0 Kudos

The only help I can provide : the tables that start with /1SEM/UC* store BCS logs

Maybe you can build a view that give you the status of the tasks and use this information as a condition in your Process chain

dan_sullivan
Active Contributor
0 Kudos

Another option instead of process chain is simply create a task group for these and execute at the group level. This will normally stop when there is an error.