on 02-23-2019 3:34 PM
Hi SAP MM Experts ,
Request your kind help on the matter as given below:
Purchase requistion release strategy is not re-triggering after made changes to PR value which is less than intially approved value. so please help me out with your inputs like is there any standard references/SAPnotes are there for this kind of behaviour.
Thanks once again for you help SAP MM Experts in advance..
Ravikumar P
Hi Ravikumar P,
It is standard behavior of SAP. If you make changes in document after approval like reducing the price lesser than the previous . Release strategy will not trigger.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ravikumar,
Please refer to below SAP note.
https://launchpad.support.sap.com/#/notes/1497235 - 1497235 - Release strategy not determined for PR in ME51(N)/ME52(N) or PO in ME21(N)/ME22(N).
Best Regards,
Lingaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.