Hi,

I have created activity element for which i have assigned "Secondary Proportionality" and referenced with Activity. When i confirm the activity with POC 10% i assume this flows to activity element. But this is not happenning. Can someone tell me what was the mistake.

Thx

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Aug 10, 2010 at 01:15 PM

    For confirmation the activity and activity elements are different objects - meaning the POC in confirmation applies only to the activity and not the element.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      I agree confirmation of activity and activity element are different. But with Secondary Proportional mesurement method one object can copy the POC of other object based on reference object. Just checking this measurement method, how it works.

      Thx.

  • avatar image
    Former Member
    Aug 10, 2010 at 05:59 PM

    Hi JJSingh,

    It should be actually reverse.

    If you select secondary proportionality as Method in actual progress field in "activity" and give "activity element as Ref. object" in that activity, then the confirmed progress (POC) from the lower activity element (when confirmed) flows to activity as secondary proportionality. Means in this example, source for POC is activity element and not activity.

    Similarly, you can even give the "activity" reference as secondary proportionality in the superior WBS Element for flow & aggregation of this POC to superior levels too.

    Regards,

    Vasu

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      It works either way...depending on the reference object. It worked with :WORK" mesurement method. "But i do not know why it did not work with "0-100" mesurement method.

      Thx.