Requirement not generating the the raw material in MRP RUN

8 Views

Hi

i created two materials one raw material and an other one is finished material

i also maintian BOM for that finished material

i also maintained all mrp views to finished material mrp type is :pd

lot size :ex

the finished material is adding to the project system

after that i run the MRP

Finished material palnned order is generating

raw material requirement is not getting

regards

vijay