Aug 09, 2010 at 07:15 AM

Problem about Inheritance in dates management

28 Views

Hi experts,I have a problem about date inheritance.

For example,I have a contract(In header and item level,different date profiles are assigned),it has two items:

10 250510W 100 EA Contract End Date changed to : 30.12.2010 (Date rule removed)

20 31P7410 100 EA Contract End Date changed to : 31.12.2011 (Date rule removed)

Then,according to our business rule,the Contract end date in header level should be In accordance with the item which has the latest Contract End Date ,that's too say,the Contract End Date in header level should equal to Contract End Date in item 20.So,I changed the Contract end date in header level to 31.12.2011,the same as item 20.

Save the contract.

Later,I add item 30:

30 40Y8318 100 EA Contract End Date changed to : 31.12.2012(Date rule removed)

And,also according to our business rule,I changed the Contract End Date in header level to 31.12.2012.

Then I found the Contract End Date in item 20 was also changed to 31.12.2012,what's the problem?

Why the Contract End Date in item 10 not changed?Just because item 20 has the same Contract End Date with header??

Can anybody explain this for me?

What's the inheritance rule from header to item level in dates management?

Thanks.

Jerry