on 08-09-2010 4:55 AM
Hi,
Can any one suggest me,
Is it possible to insert production requirement date field in the QA32 screen ? advantage of this field is based on this Quality will give priority of the inspection lot otherwise because of this batch hold the next stage of production.
Krish
Nothing standard. But you could use a user exit at the time of inspection lot creation to copy the production date requirement into the short text of the inspection lot. This can than be displayed in QA32.
Keep in mind it will not be automatically updated if changes are made on the production side.
FF
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
As far as I know, no such standard field is in there. But custom field might be added. Discuss with ABAPer.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
15 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.