cost element catogery change

Former Member
0 Kudos

Dear Experts,

Pleae guide me, how to change the cost element catogery from sales deduction (12) to primary cost (1), till now data not exist in gl code. if i change from 12 to 1 catogery any implications?

this will be appreciate,

Regards

Chandu

Moderator: Please, search SDN; it has been asked several times

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You can change the cost element until you donot have any postings to GL. Cost element category 12 is used for discounts etc..whereas cost element category 1 is used for primary this GL should be assigned to cost object i.e cost centers, internal orders etc..

Regards,

Sreekanth