Dear guru.
I have a bom with two alternative item (A and B) with same group.
I need that mrp create dependent requirement only for A and nothing for B.
After atp check if B is available and A isnu2019t available I need that the system create requirement for B for the available quantity and create requirement for A for the remained quantity.
How can I set the alternative item data group of bom for these two component ?
Thanks.
Hi,
I hope that I understood you right;
The set up of the alternative item group in the BOM should be like this:
Priority - 1 for A, 2 for B
Strategy - 1 for both
Usage Prob. - blank for both
Alternative item group - same for both
Now this works like this:
MRP will always plan A.
When ATP is checked in production order it looks first for A. If A not available or available quantity not enough, then it looks for B.
Be aware of system behavior when using this with backflush and overproduction! There is a note on this!
Regards,
Mario
Hi.
Thanks for your interesting.
With your suggestion the system donu2019t have the behavior that I need. If A and B arenu2019t available the system donu2019t create any dependent requirement for nothing.
I have tried with this setting :
Priority - 1 for A, 2 for B
Strategy - 2 for both
Usage Prob. u2013 100 for A blank for B
Alternative item group - same for both
If A and B arenu2019t available all the dependent requirement is create for A.
If B are completely available and A not , all the dependent requirement is create for B.
The problem is concerning when A isnu2019t available and B is partially available , all the dependent requirement is create for A , the system donu2019t split the requirements.