Production Order

HI EXPERTS,

In the T-Code COOIS, when i Click "Go to" then "cost" then "analysis", i can see the planned cost and actual cost there.

But my question is, where does planned cost came from in the cost analysis?

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Feb 19, 2019 at 06:20 AM

    To put it briefly planned cost comes from production order calculation.

    To elaborate a bit - each production order has at least one operation. The operation is performed on a work center, the work center is assigned to a cost center. The operation generates activity requirements. You maintain the activity rate (price) per activity type / cost center. Taking into account activity requirements generated by production order operations and activity rates SAP calculates the planned cost of your operations. That's one part of production order calculation.

    The other is the planned costs of production order components. They are calculated based on your bill of materials.

    Best regards

    Dominik TylczyƄski

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.