Hi Experts,

when i am executing RPTEDT00 Report or PT61 T Code. I am getting the following error though i have done Time Evaluation successfully.

No time evaluation data available for the period

Please suggest me what i need to do to get the Time Evaluation Results.

Regards,

Dolly

Accepted Solutions (0)

Answers (2)

Answers (2)

waqas_rashid
Contributor
0 Kudos

Hi Dolly,

Have you maintained infotype 7. If yes, then plz check time management status. Or else check the validity period of infotype 7 record.

Regards,

Waqas Rashid

Former Member
0 Kudos

Hi Waqas,

I have maintained infotype 7 and time status is 1 Actual time. i have maintained validity date from 01.01.1900 to 31.12.9999. Apart from this any other solution do u have .

Thanks & Regards,

Dolly

waqas_rashid
Contributor
0 Kudos

I think the period for which you are trying to print time statement, time time evaluation (tcode PT60) is not performed for that period. That is the reason you are getting this (No time evaluation data available for the period) message.

Please make sure, test run check box is unchecked when you execute time evaluation.

Regards,

Waqas Rashid

Former Member
0 Kudos

Hi Waqus,

I have checked all the options that u have mentioned. still i experience the same problem.

Regards,

Dolly

Former Member
0 Kudos

any answers please.

Regards,

Dolly

Former Member
0 Kudos

Any Answers Please.

Regards,

Dolly

waqas_rashid
Contributor
0 Kudos

Hi,

Please try your time statement with some other form. Form name parameter on selection screen of PT61.

Regards,

Waqas Rashid

Former Member
0 Kudos

Hi

I have got the form, i have done by copying other country form to 40 and executed it.

Thanks to all.

Regards,

Dolly

Former Member
0 Kudos

Hi,

Is for this report (PT61) Time Management Status - 1 is mandatory.

This report will not work when the Time Management status is 9.

Please confirm

Former Member
0 Kudos

Which view need infotype=7? in PA30 transation I see different views where I can insert infotype 7...

And where I set the status?

Sorry fo those questions, but I have to learn Time Statement and I haven't found a sort of starter guide.

Thank you

Kind Regards

MImma

Sanky
Active Contributor
0 Kudos

Hi Mimma,

It's already a closed thread.

So please create a new thread with your query briefly mention.

Regards,

Sankarsan

siddharthrajora
Product and Topic Expert
Product and Topic Expert
0 Kudos

this error occurs when there is no data in clusters in PT66 for the pernr to be displayed in PT61

So please check if the data is there in B2 for the pernr for specififed period

Former Member
0 Kudos

Hi sid,

Thanks for the Response.

I have checked the B2 Cluster i have data in that for the specified period. I have check all possible ways of inputting the data but every time its throws the error.

Please guide if there is another way to get it.

Regards,