cancel
Showing results for 
Search instead for 
Did you mean: 

one production order

Former Member
0 Kudos

I have one production order for finished good A, but finished good got semi-finished component AA and its child AAA and AAB, also we have raw mat. AB, in order master data, I can only see one line of semi-finished product AA, with price 20, semi-finished good using S price control, so Is 20 standard price or moving avg.price?

I don't have separate order for AA(semi-fin.), so how can I know the actual price and quantity issued for AAA and AAB by looking at production ord. table?, in the table, I can only see price for AB and AA.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

As per the structure of the BOM(CS03) for the finish material A, it will show the prize of AA & AB material. It is right because it has direct link. But AAA & AAB is linked with semifinish material AA , not for the finish material A. So, it will not consider in finish material A product cost.

semi-finished good using S price control, so Is 20 standard price or moving avg.price?

For prize control S - system will consider standard cost 20, not moving cost.

If you want to check the prize of AAA & AAB prize in absence of production order in cost estimate CK13.

Rgd,

Chetan