what are the steps to create delivery schedule lines against document type LPA and how to release without using MRP run, JIT schedules or Forecase schedule. In normal SA we need to create manual Delivery schedule lines and want to release to vendor time to time.
We are not using MRP / JIT Schedules or Forecast schedules.
Thanks
Sathya
See my answer in your duplicate question: Release for Delivery Schedules Against SA without MRP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Diana Dai
Thanks for update.. but the requirement is if we use LP doc type there is no record for validations or Vendor evaluation or when it release and when the goods received.
The requirement is to go delivery schedules through release document as output to Vendor.
Thanks
Sathya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Sathya,
If releases with JIT or FRC are not expected, you can consider to using SA order type LP (not ticked with release document indicator) for creating schedule agreement, and use ME38 to create the schedule lines manually.
Best regards,
Diana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.