cancel
Showing results for 
Search instead for 
Did you mean: 

Single planned order to cover multiple shortages inside PTF

Former Member
0 Kudos

We have an MRP requirement to consolidate shortages on different dates inside the planning time fence into a single planned order at the planning time fence. The single planned order quantitiy must equal the total of the shortages and no more. 'Lot-for-lot' lot sizing almost gives us what we need, however it results in multiple planned orders (i.e. one for each shortage) in stead of a single planned order.

Any suggestions?

Thanks,

Laurence.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can use the special period based lot size for e.g monthly, weakly or even you can define your own lot size

as per your required. According to this lot size you can combine the requirement in that period & create one

planned order or purchase requirement..

Rgd,

Chetan

Former Member
0 Kudos

Thanks Chetan.

I had thought of that. The downside of this approach is we have many different PTF lengths for different materials, so we will need to configure many period lot sizes.

Regards,

Laurence.

Former Member
0 Kudos

This message was moderated.

Answers (0)