on 07-29-2010 6:01 AM
Hi All,
iam new in pp,My client is in traiding not in manufacturing ,they need to config system for mid term & long term planning with mrp run for procurement only instead of production.how we can map in system.can provide steps.
can we do sop without production planning,what will be the flow?
If any body having document on sop please provide me.
Regards
Gajendra
Hi Gajendra,
1. Since you are a trading company no production is done ,but procurement and sales will be part.
2. Make your material as externall procured and proceed with the MRP planning.
3. you can use the SOP for doing demand mangement
4. This [SOP LINK|http://sap-pphelp.blogspot.com/2010/01/sales-and-operations-planning-standard.html] Will give you a fair idea on the SOP.
5. Try the above and later post with specific querries
reg
dsk
Edited by: Dsk on Jul 29, 2010 10:42 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, you can do S&OP for trading. You enter sales plan in S&OP, transfer to Demand Management as Planned Independent Requirement, then run MRP. The output is the PR that generated. You can review PR and convert them to Purchase Order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.