on 07-28-2010 4:24 PM
Hi,
When creating the Asset master data, the user sometimes update an inactive/blocked cost center and this will be noticed only at the time of Depreciation run. Is there a way to notify the User at the time of creating/changing the Asset master data that the Cost center is blocked.
Do you have any solution for this?
Regards,
Vinod Chandran
Hi,
I don't think there is an option to notifiy the user while changing the cost center in a standard way.
1) Go for an enhancement in asset master at create/change level or you can try validation user exit at asset master level (GGB0)
2) Create a query linking ANLZ and CSKS to bring out locked cost centers which are assigned in asset master. This report has to be executed before depreciation run.
Best Regards,
Madhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.