Hello,
Production order date mismatch between ECC & R/3
Back Ground :
1.If in the Routing we have operations 10,20,30,40,50,60,70,80,90,100
2.Only Operations which have run time are cifed to APO depending on Control key (ie operations :20 40 ,60) and scheduling relevent
3.Que time is maintained in Work center and work center is assigned to 10,20,30,40,60,90 operations
4.Operations are start - Finish relation ship
5.All calenders ,resources and master data in sync
6.Using PDS
Questions :
4.The Production order dates don't match in ECC & APO ?
1.When all the operations are not cified to APO ,will the Basic dates match for Prod Order in ECC & APO?
2.How does the above basic date calculation work,when orders are converted in R/3?
3.would APO use PDS to Recalculate calculate the lead time ignoring the basic dates send from R/3 for Production orders(Converted in R/3)?
Please let me know if need to check some other config points
Thanks in Advance
Regards,
Kamala