on 02-14-2019 8:55 AM
Hi experts,
We have an page in the PCD that is checked out by an user that doesn't exist anymore. Now we are unavailable to change things. How can we change the status of this object?
thanks in advance,
Vo
Hi Nick,
via the PCD editor I could change the settings thanks.
Vo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nick,
there are no objects locked in the monitoring, I already checked it.
System restart isn't an option for our production environment, are there no other options?
gr
Vo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can try modifying the object via PCD Inspector tool:
Hi Vo,
Go to System Admin -> Monitoring -> Object Locking. See if you see the object there and remove the lock. If the problem remain restarting the Java engine should release it.
Nick
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.