Friends,

We are using statistical internal order budgeting purpose. We made internal order field mandatory for Account assignment category u2018Ku2019.

There is a requirement of budgeting maintenance expenses which have account assignment category u2018Fu2019 (used for Main. Order).

Do we have any option where I can provide account assignment Maint. order as well as Internal order (Statistical) for purchasing documents/ or any workaround for this situation.

Thanks in advance.

Om Tiwari

Accepted Solutions (1)

Accepted Solutions (1)

iklovski
Active Contributor
0 Kudos

Hi,

No, maintenance order and internal oder could not be entered simultaneously into one document. You might use statistical WBS for this purpose; then, you can enter maintennance order for assignment and WBS for budget control.

Regards,

Eli

Former Member
0 Kudos

Hi Eli,

Thanks for reply... here want to use only internal order for budgeting.

Is there any way to budget through statistical internal order.

Regards,

Om

iklovski
Active Contributor
0 Kudos

In this case you won't be able to assign your POs to maintenance orders, as every document (item) could be assigned only to one order, no matter the nature of it.