on 02-19-2019 4:43 AM
Hello Expert,
We are executing performance base preventive maintenance based on counters and measuring documents creates upon production confirmation.
My requirement is to get Production work centre(Operation PRT assigned) into IK17 report. So that it's easy to locate the PRT in the facility, Is there any user exit or is this available in standard?
Thanks in Advance
Ashok