on 07-28-2010 5:40 AM
Hi All
I have created three activities in my project.
Activity 1 - start date 28/07 to end date 06/08 duration - 10 days
Activity 2 - start date 07/08 to end date 23/08 duration - 15 days
Activity 2 - start date 24/08 to end date 14/09 duration - 20 days
In actual when i confirm activity my 1st activity get delay from 4 days
Activity 1 - start date 28/07 to end date 10/08 duration - 14 days
when I check in report system not show any delay. how we would get delays for the activity. also when i reschedule its consider 11/08 is start date for my second activity but never indicate anywhere delay of activity in project plannig board or gant
chart. can any one gives inputs on same.
Regards
I dont think you will see delay in Gantt chart, however you can see delay in structure reports, check the fields available for structure reprot of activity. and regarding your second query, Why system consider the 11/08 as start date for activity 2 after rescheduling, check in SAP HELP.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ahmed,
I already search structure related report CNS41 in which delay column its don't show any values but in earlier, later and past out of which three column its show delay if its previous then start date & later if it was later then end date. but not any value in delay column as activity delay by 4 days as also its show diff in duration and actual duration by 4 days.
Why system consider the 11/08 as start date for activity 2 after rescheduling ??
due to my first activity delay by 4 days and FS relationship maintain between each activity after rescheduling system calculate new date for 2nd activity as start date after 4 days ie 11/08 insted of 07/08.
My question is still pending about delay in activity.
Regards
Hi Ahmed,
I had created project & Network, I had assigned the WBS to the activities and to that activities I had done the FS relationship & then I had schedule the Project. Now I am going to CJ20N & scheduling at the project level using bottom-up scenario. Scheduling gives proper dates.
28.07.2010 to 07.08.2010 duration 10 days
09.08.2010 to 25.08.2010 duration 15 days
26.08.2010 to 17.09.2010 duration 20 days
I confirm my first activity and it delay by 4 days. so now my dates changes as per delay of first activity
28.07.2010 to 12.08.2010 Actual duration 14 days
13.08.2010 to 30.08.2010 duration 15 days
31.08.2010 to 22.09.2010 duration 20 days
In all four column (Delay,Earlier, Later, Past its show no values)
Regards
Yes you wont see any values, because system calculates delay by comparing your actual finish and latest scheduling dates. i.e., Actual finis date - Latest Sch. dates. In your case, you have rescheduled the project after confirming and because of that latest sch. date of activity has been changed, i.e., it is changed from 07.08.10 to 12.08.09 due to full confirmation. So, now
actual finish - Lts. Sch. date = 0. So you see 0 value in your report.
Pramila Mhatre,
The delay is calculated when the actual finish date is beyond the latest finish date, in your case actual date 12.08.2010 must be <= to the latest finish date of that activity. Please check.
The same logic also applies for the rescheduling.
You may also refer the link for more info http://help.sap.com/saphelp_erp60_sp/helpdata/en/c0/1885347860ea35e10000009b38f83b/frameset.htm
Regards,
Praveen
Hi All
I have first change in configuration remove tick Schedule automatically from Parameters for Network & WBS scheduling to avoid automatically scheduling after status change. Now again create project as same order with three activities
Activity 1 - start date 29/07 to end date 09/08 duration - 10 days
Activity 2 - start date 10/08 to end date 26/08 duration - 15 days
Activity 2 - start date 27/08 to end date 18/09 duration - 20 days
Now in actual when i confirm my 1st activity by 50% completion (not 100% or final confirmation) consider actual finish date 17/08 ie duration 17 days instead of 10 days and save. In dates i see latest date for this activity not change as I remove auto scheduling tick
Activity 1 - start date 29/07 to end date 09/08 duration - 10 days
Activity 2 - start date 10/08 to end date 26/08 duration - 15 days
Activity 2 - start date 27/08 to end date 18/09 duration - 20 days
In actual start date for activity 1
Activity 1 - start date 28/07 to end date 17/08 duration - 17 days but still in reports Delay,Earlier, Later and Past its show no values. In my case Total & free floats is zero.
Regards
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.