cancel
Showing results for 
Search instead for 
Did you mean: 

purpose of IM52 in IM

Former Member
0 Kudos

Can you please explain the purpose of IM52 transaction in Investment measure.

Can we have two approval years for one project, while using investment program ?

when you make budget in Im52 with reference to project,we can you budget for all financial year other than Approval year.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member375980
Active Contributor
0 Kudos

IM52 is used to distribute the budged from investment program to the investment measures (either WBS or order). You can distribute the budget to the approval year only.

Blaz

Former Member
0 Kudos

Project(s) budget (like all other budgets) is maintained either annually or overall. If you maintain annual budgeting, when you close the current approval year, you will have the option of carrying forward remaining budget to new approval year (hence, no concept of attaching a project to different approval years).

When current approval year is closed then measures (WBS or orders or appropriation requests) will be attached to new approval year with remaining budget (in case of annual budgeting).

Former Member
0 Kudos

problem solved.