on 07-27-2010 8:30 AM
Hi All,
If I create a purchase requisition with item category D (services) and I use a service master with a valid price in service condition maintained via ML5L, is the price then automatically retrieved in the PR line by standard SAP??
If this is not standard, is there an user exit which can be activated to retrieve the price from condition and copy it to the PR service line.
Please provide me with possible alternatives/solutions for retriving price from service condition to PR service line.
Regards, Kannan.
Hi All,
If someone is aware of PR price getting picked from Service Conditions, please advice.
Regards, Kannan.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kannan,
this is the normal system behaviour.
If in a purchase requisition (PR) you maintain services for which
service conditions were maintained, you can still change the price in the PR
manually. Please also consider, when you create a purchase order (PO) later on, the system uses the
price from the condition, not the manually changed price from the PR.
The system uses the net price from the service master also in a PO.
The system takes always the price from service condition
if there is a condition.
Please check if using by EXIT_SAPLMLSP_030 you could change this behaviour according to your requirements.
Regards,
Edit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.