on 07-27-2010 5:06 AM
Hi Experts,
Is it possible to group the Resources/Workcenter at a header level (Say a header resource or with a department name)
My client requirement is
Initially the Resource was made only for 8hrs availability, but as and when required he will make the resource available for additional hours by extending the time interval for Capacity Evaluation
But it is a tiredsome work to extend the time for each and individual resource
His expectation is can the resources be grouped at department level and thereby we can change the Shift Timings at Resource group level rather than extending the shift timing for individual resource
Appreciate your help in advance
Regards,
Tam
Hi,
SAP has a functionality called as Workcentre hierarchy .These are like logical grouping of the individual workcentre to collectively view them in the md04,mf50 etc.
But in your case u are planning to adjust, this is not possible,
SAP expects the data at the workcentre level.
explore the possibility of useing the workcentre hierarchy and also using some tools like ( bdc, lsmw) to change the capcity planning .
Reg
Dsk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.