How to figure out to which PR planned orders are assigned in MRP

Dear experts,

in MD04 I see planned orders unter purchase requisitions (PR).

How they are linked? Is there a like anyhow?

How ca I get related Planned orders for PR or PR for planned orders?

Many thanks in advance.

Best regards

Patrick

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Dec 02, 2016 at 03:53 PM

    Hello Patrick

    There is no fixed link between the requirement and the replenishment element generated by MRP. You can try to use transaction MD09, where system dynamically tries to find this link. See my answer on thread https://archive.sap.com/discussions/thread/3414449 for more details.

    Regards,

    Caetano