Anyone had this issue in CHARM before ?

we have SLFN - SDCR - SDMJ open for a change.

Development complete and almost tested - transport of copies is in QA, but original transport is not released from DEV.

Business now wants to stop this change and close SLFN.

How can I close/cancel SDMJ ?

When I try to cancel it, I get the message "Changes in development system are not excluded" and status is not changed.

Is there a way to force close SDMJ ?

Thank you

Elena

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thank you Lori,

I agree it's right think to reverse the change and still move it all way thru to PROD, then close the ticket.

Former Member
0 Kudos

>

> Anyone had this issue in CHARM before ?

>

> we have SLFN - SDCR - SDMJ open for a change.

> Development complete and almost tested - transport of copies is in QA, but original transport is not released from DEV.

> Business now wants to stop this change and close SLFN.

>

> How can I close/cancel SDMJ ?

> When I try to cancel it, I get the message "Changes in development system are not excluded" and status is not changed.

> Is there a way to force close SDMJ ?

>

> Thank you

> Elena

Elena, the system is giving you this message as a (cryptic) reminder that even though you want to close the SDMJ, you have made changes in DEV and QA that need to be reversed with another transport. Depending on your audit requirements, you may want to add these reversing entries on the same transport as a new task, or on an additional transport and send the whole thing through the normal processing. The other alternative is to execute CRM_SOCM_SERVICE_REPORT - just make sure you have reversed the changes already made to maintain the integrity of your landscape.