Hi Gurus,
When we execute CN41N, Materials assigned to the Network activity are visible but the cost of each material is not getting displayed against it (under Proj. Cost Plan Column) and it is appearing as '0' whereas, it is appearing as an accumulated cost against the activity. I checked SAP notes for this problem, though I could see some notes which are very close to the problem but all are for Release 600 whereas we are using 604 (ECC 6.0). Have anyone encountered such problems or whether the cost will not appear against Material in CN41N.
Awaiting your valuable suggestions.
thanks in advance.
Vinodh
this is not a problem but std behaviour
material although assigned to an activity are costed at the activity level if the activity is account assigned as per the network type
I have seen planned cost of material against material itself in structure report like CN41, CN41N under following conditions:-
1. Valuated Project Stock
2. Material is created using Reservation for WBS or PR+Res for WBS Procurement indicators.
3. Costing relevancy box ticked for material
4. Statistical Cost element exists for Inventory account.
I have not seen planned cost for non-stock item or material with res for network in project. This is purely based on my experience and I dont have any notes or help document to validate my statement.