on 02-18-2019 6:13 PM
Hi,
How can I run MRP only on last thursday of every month for specific materials ?
Thanks for your help
Regards,
Venkat
Alternatively you may consider using Time-Phased Planning according to planning calendar - check out SAP Help documentation: Time-Phased Planning
The previous answer mentioned selecting materials during total MRP run. You may read on that on SAP Help: User Exit: Material Selection for the Total Planning Run
Dominik Tylczyński
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you Tylczynski.
Regards,
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Venkata,
Background job SM36 scheduling is no possibility to run MRP last Thursday of every month.
In this case, you can check selection variable condition options during MRP variant creation with technical (ABAP) team or contact BASIS team to explore any other options. variant.png
For time being schedule multiple jobs every month predefined date (Thursday) selection manually.
Best Regards,
Lingaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.