Hello,

we are using Inspection type 03 for in-process inspections and a control key that needs confirmations (2).

in Result Recording QE51N, after completion of results recording for characteristics, the system jumps into a dialog box for confirmation of the operation quantities (yield, Scrap, rework). To enter inspection times for the operation it is necessary to press the button ‘confirmation’ in this dialog box. But the system does not use CO11N as expected but the old transaction CO11. For us it is vital to use CO11N since our PP-department will have some new fields in CO11N which are relevant for confirmation and which will not be shown I assume.

I have already searched in Q&A database but I cannot find how to switch from CO11 to CO11N in Result Recording?

What do we have to do to switch from CO11 to CO11N in Result Recording??