on 07-23-2010 10:49 AM
Dear Experts
i am preparing a shipement cost document wherein i have maintained the setlement date as "0004"-stage start actual.
The problem what i am facing is that the user wants to change this date at the time of transferring the cost to accounting but when he tries to open this shipment cost document in VI02 this field "settlement date" is greyed or freezed.
I wish to change this date according to my will.Kindly advise as to how this can be done.
Regards
Sanjeev
Hi Sanjeev,
Pls assign settlement date as "0002-Stage End (Actual)/Current Date" in Tcode T_56. Alslo note that settlement date is proposed internaly ,however if you want to post it on a date different from date of transfer to accounts than creat the Shipment cost document via Tcode Vi01and give the desired settlement date.
The PO can be invoiced subject to open of FI period.
Hope your issue would be resolved.
Regards
Sanjay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.