Hello,

I am arranging the Test Sequence according to business requirement. In the below screenshot I need to arrange Test Case number 1 again at number 8. Please advice.

Thank you.

Best regards,

Rohan Shirude

ts.jpg (598.7 kB)
Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    Feb 20 at 07:59 AM

    Good morning Rohan,

    you could only assign the same test case twice in your sequence if you have the same test case assigned a 2nd time within your solution documentation.

    Best regards,

    Sylke

    Add comment
    10|10000 characters needed characters exceeded

    • Thank you so much Sylke for the answer will do the same but now the issue is that during our End-to-End testing there are so many Test Cases are repeated at so many times and this is generally happens as well that Test Cases are repeated multiple times during end-to-end testing.

      It's really surprising that "Test Sequencing" functionality can not have the option to choose a single test case at multiple times and arranging into the sequence accordingly

      Well just a thought that if we can have some option in "Sequence Number" column e.g. we can put 1 & 8 or 1 : 8 something like that so Test Case number 1 can also be at sequence number 8?

      Thank you.

      Best regards,

      Rohan