Can you give some link or information about SAP MM link with Project system how it interface how to manage the material and inventory in Project system.
regards,
zafar
Hi
In case of Project procurement either with P/Q Account assignment category ,PO will be linked with the WBSE element and the project stock will get updated upon GRN. Project stock will be stored in MSPR Table
221Q movement in MIGO is GI from project stock
Regards
Amuthan M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for your relply i need some other basic information is there any other way of creating material master or it is same as we are creating normal material master and after PO with account assigmen tP/Q is there any different process for GR MIRO etc. or remaining all are same.
regards,
zafar