on 07-21-2010 10:30 PM
Hi,
My user has sales order in which he has used Mile stone billing
The Billing is being done in two shots - 60% once and the second time 40%
60% has already been invoiced and the 40% is creating a problem and they want the sales order to be closed
In one of the custom reports- it says that the 40% (mile stone number) is assigned to multiple sales orders and so the sales order cannot be confirmed
I am totally new to SD and so request to kindly explain high level concept and also provide the solution
Thanks,
SS
Hi,
Is your line item in sales order assigned to wbs elements?
If it yes?
check milestones may also comes from it- check with PS consultant-
you can also check milestome number and billing plan number- if you display milestone
Use CN41 transaction to check sales orders assigned to WBS element
uou can refer Table: FPLT
ICN53n-report
Thanks
Buddi Chidambaram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks a lot for the prompt response
I do not have access to any of the tables/transactions you have mentioned
But to answer your question- YES, the sales order items are associated with WBS elements
Is there a way in which we can close the orders now by delinking the Mile stone assignment to multiple sales orders?
Thanks,
SS