MILESTONE BILLING- Mile stone assigned to multiple sales orders

Former Member
0 Kudos

Hi,

My user has sales order in which he has used Mile stone billing

The Billing is being done in two shots - 60% once and the second time 40%

60% has already been invoiced and the 40% is creating a problem and they want the sales order to be closed

In one of the custom reports- it says that the 40% (mile stone number) is assigned to multiple sales orders and so the sales order cannot be confirmed

I am totally new to SD and so request to kindly explain high level concept and also provide the solution

Thanks,

SS

Accepted Solutions (1)

Accepted Solutions (1)

bcrao
Active Contributor
0 Kudos

Hi,

Is your line item in sales order assigned to wbs elements?

If it yes?

check milestones may also comes from it- check with PS consultant-

you can also check milestome number and billing plan number- if you display milestone

Use CN41 transaction to check sales orders assigned to WBS element

uou can refer Table: FPLT

ICN53n-report

Thanks

Buddi Chidambaram

Former Member
0 Kudos

Hi,

Thanks a lot for the prompt response

I do not have access to any of the tables/transactions you have mentioned

But to answer your question- YES, the sales order items are associated with WBS elements

Is there a way in which we can close the orders now by delinking the Mile stone assignment to multiple sales orders?

Thanks,

SS