Forecast (Independent Requirements) release from APO to ECC

Former Member
0 Kudos

Hi All:

After upgrading our APO system to 7.0 when we release the forecast to ECC, I do not see the transfer data coming over to ECC.

I checked the process chain log and I could see the list of product/location for which the log says transfer was successful. I do see some errors but those are expected for those product / location. I check ECC using SLG1 and there were 3 expected errors (material marked for deletion, etc). But I do not see the transfer. What am I not doing right? The process chain has a job that has an activity with a Transfer release profile. This profile (in Quality system) is an exact match with what we have in Production.

Pl. help.

Thanks

Ryan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Have you activated the all the integration models after the upgrade

(1) PLANT

(2) MATERIAL

(3) PLANNED IND REQ

Try this and let us know

Thanks

Kumar

Former Member
0 Kudos

Hi,

You might be checking already correctly.

Are you checking in the correct version of SAP ECC ?

From your posting, it looks you are following all the steps as below:

1. Create a transfer profile.

2. Create an activity.

3. Create a planning job.

4. Schedule the planning job.

5. Review the job results in the job log

Link for SAP Help just in case:

http://help.sap.com/saphelp_scm70/helpdata/en/5f/176d4160168147e10000000a1550b0/frameset.htm

regards

Datta