Customizing Path for Table T681Z ??

Hi all,

Can anyone guide us the table T681Z setting change SPRO customizing path.

Thanks

Vijay

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jul 21, 2010 at 10:48 AM

    HI

    Please follow the path

    SPRO - MM - Purchasing - Conditions - Define Price Determination Process - Extend Field Catalog for Condition Tables

    Thanks & Regards,

    Mani :

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 27, 2010 at 11:54 AM

    Hi

    Modify setting in table T681Z for OA archive, as below:

    B E1 001 KOMKBE1 BUS2015 RV12LC00

    We need to modify the table seetings as above.. whr i can find the customizing..

    Thanks

    Vijay

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.