on 07-20-2010 4:26 PM
Is is possible to ajust settings or use BADI so that when executing a Cancellation of a document via MIGO, the "Reason for movement" field (MSEG-GRUND) is copied form the reference document to be cancelled ?
Hi,
If you use transaction MBST, to cancel the goods movement, the field MSEG-GRUND will be copied to the cancellation document.
Kind regards
Jorge
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Guillaume,
Try in customizing SPRO:
Customizing:
-> Materials management
-> Inventory management and physical inventory
-> Physical inventory
-> Default values for physical inventory:
For each plant in which you use the reason code, you can
enter a default value.
Hope this helps,
Adam.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Adam but we do not want to have the same reason for movement code for the organisation; we want the reason code to be copied from the reference document we are cancelling.
We tried to use method LINE_MODIFY in an implementation of BADI MB_MIGO_BADI but the field GOITEM-GRUND is not modifiable (message MIGO-050).
Any clue ?
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.