on 07-20-2010 11:32 AM
Hi,
in Master Material in view MRP4, in "Individual/Coll", it is shown:
"If a material managed in project stock is to be procured from another plant using a cross-company-code stock transport order, the indicator must be set to 2 (collective requirements) in the issuing plant because, in this specific context, individual project stock management is not possible in both plants".
I would like to know why it is not possible, and if it could be possible to change the SAP Standard in order to allow it.
Thanks in advance,
Luis.
You should use Individual/Coll as blank. In that case you can use functionality of Project Stock and Plant stock.
With Regards
Nitin p.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nitin,
thanks for your quick response. That is true, but even if I do that, I still have a problem because I need to deliver my material from project stock in plant A to project stock in plant B, and this should be done in just one step (I can't move my material from project stock to unrestricted stock in A and then send it to B because it will modify the medium average price.
In other words, i would need movement 643 to work with project stock (from proj. stock to proj. stock) or find an alternative solution.
Regards.
User | Count |
---|---|