Hi Experts,

I am working with DM module of SAP ISU. Currently I am facing a problem that after move-in a periodic order with RR 01 is created automatically by the system.

Ex: Move in date is 01.01.2010. Monthly Portion is used with Schedule record 01.01.2010, 01.02.2010, 01.03.2010, 01.04.2010 and so on.

If current system date is 20.07.2010 then Meter reading order is created automatically by the system for sch MRD 01.08.2010.

Please let me know how to overcome this problem

Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jul 21, 2010 at 09:39 AM

    Thanks for your reply but I have cheked SPRO setting the suggested check box is already uncheked.

    I beleive the setting you have suggested is meant for default meter reading during move in but my problem is automatic creation of meter reading order with reason 01 during move in

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Thanks a lot, your suggestion has resolved the problem. Mentioned SPRO field value was maintained as 100 in my system tha's why it was creating MR order automatically during move in.

  • avatar image
    Former Member
    Jul 20, 2010 at 02:01 PM

    In SPRO

    under sap utilities->Device Management->Meter Reading->Basic Settings->Define Control Parameters for MR Data Processing

    double-click on the line and verify the check box for Display Default Move-in value. Try un-checking the box.