cancel
Showing results for 
Search instead for 
Did you mean: 

DataSource 0PM_SCH_PLND_ORDER; switch to package EAM_EHP4_SR_SF

Former Member
0 Kudos

Hi Experts,

I'm trying to activate a datasource 0PM_SCH_PLND_ORDER Scheduling Overview and Planned Order in ECC, but got this error:

DataSource 0PM_SCH_PLND_ORDER; switch to package EAM_EHP4_SR_SFWS_SC is off

Please help. Thanks!

Ting

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Error message:

DataSource 0PM_SCH_PLND_ORDER; switch to package EAM_EHP4_SR_SFWS_SC is off

Message no. R8371

Former Member
0 Kudos

Hi,

I am having the same problem when I try to activate the datasource 0PM_SCH_PLND_ORDER. Can you please let me know how did you resolve the problem?

Thanks,

SB

Former Member
0 Kudos

The problem has not been resoulved. I'm still have the same problem.

Former Member
0 Kudos

It was fixed by switch on the Business Function Set LOG_EAM_CI_3 using t-code SFW5