Hi

I have a bit different scenario: raw material is batch managed. Now at the time of GRN in MIGO, the no. of line items for the same material varies. Sometimes its 25, sometimes 30 and so on.

Now the requirement is, can we control the inspection lot creation at the time of GRN. For example, when 25 line items, only 2 lots should go to quality. When line items are 50, 5 lots should be available in QA32, rest will be skipped.

In simple words, like sam[ling scheme, we need a scheme for no. of lots to be craeted for quality.

Any input on how to map that in SAP?