07-14-2010 8:20 AM
Hi All,
I will approve my request numbers to transport to Production from transaction STMS_QA in Quality system by choosing approval step and then clickikng on APPROVE.
But I want to approve my colleague requests from STMS_QA in Quality system. How can I approve the other requests. Please suggest.
Thanks,
Ganesh.
07-14-2010 8:36 AM
Ganesh,
Why do you want approve your colleague requests in Quality system .? why not your colleague itself?
Thanks,
Sri
07-14-2010 1:24 PM
Thanks Sri,
I got the answer. My colleague is on vacation and he requested me to approve the request in STMS_QA to import to PR2 as we have a monthly schedule job runs once in a month to import to PRD.
I clicked on Approval step in STMS_QA and I noticed there is a option to change the owner of the request and changed that to my colleague ID and approved.
Thanks,